UPDATE - 5/16/22:
the bridge closure was changed back to May 16-20. The contractor failed to notify the Township and the school.
Original Post
CABIN CREEK RD CLOSED – BRIDGE WORK
5/18 – 5/23/22
Due to inability to get paving material and rain delays, there is a revised schedule for Cabin Creek Road bridge closure. The dates for the closure for Bridge 271 is now May 18th thru May 23rd.